Permit Application - Water Heater (Gas or Electric) 

Resident Information

Plumber Information

*** If this is the company's first time doing work in the District, a PLUMBING PERMIT REGISTRATION FORM must be completed and turned in with this application.

Requirements

1. All plumbing must comply with the current Uniform Plumbing Code and TCEQ regulations. Any health hazards found in existing plumbing must be repaired.

2. An inspection must be completed by the District's inspector, listed on the permit, within 1 week of installation.

3. If the prepaid plumbing inspection fails, the above company will receive a bill for the re-inspections. Re-inspection fees are $65.00 each. All re-inspection fees are due 10 days after receiving bill or the above company will be terminated from the District.

NOTE: To ensure contamination of the public water does not occur, all backflow prevention devices must be tested upon installation and every 5 years thereafter. All backflow devices that are installed to protect against health hazards must be tested annually. This is to be done by a certified tester and a copy must be filed with Brushy Creek M.U.D. This testing will be at the home owner's expense.


Please SUBMIT below___This section is for Office Use Only