District Projects : IN PROGRESS : Pepper Rock Park Improvements

Pepper Rock Park Improvements

February 26, 2018 Update:

The park with the most to be completed is Pepper Rock Park. The first month has been spent removing all the old playground elements, swings and much of the sidewalk as well as preliminarily placing the layout down for site review by the landscape architects and staff.  During this time, the tree protection fencing was down as the construction crews were taking their measurements for the layout. Over the next few weeks, equipment will begin the grading process for all of the areas. The new playground equipment and site amenities will begin their installation in late March and April.  Pepper Rock Park is currently scheduled to complete its part of the overall project in early May.