District Projects : IN PROGRESS : Water Treatment Facility Generator Automatic Transfer Switch Improvements

Water Treatment Facility Generator Automatic Transfer Switch Improvements

Location: Water Treatment Facility

Estimated Time Frame: Work for this project was completed in 2024. 

Description: Work on this project includes improvements to the facility's existing automatic transfer switch to ensure power continues to be transferred smoothly to a generator, allowing for uninterrupted water service in the event of a power outage. 

Impact to Community: No residents will be impacted while work for this project takes place. The project allows the District to have a resilient and uninterrupted water supply in the event of a power outage at the water treatment facility. 

Contractor: Power Quality Engineering, Inc.

For more information, reach out to the District team at projects@bcmud.org.